Installation of window structures in the first house is underway
RIEL Real Estate Corporation reports that in the first stage of Nordica Residence RC in the house No. 1, window structures are being installed, brickwork is being carried out on floors 22, 23, 24, 25; the arrangement of the ramp and internal networks in parking No. 1 and the roofing of the house are starting. This was announced by the project manager.
At the same time, in the second stage, monolithic vertical elements on the -1 floor are being carried out in the house No. 2, and in the house No. 3, the work on excavating piles, pouring concrete preparation and installing a foundation slab begins.