In the first section, the slab of the 10th floor is cast
RIEL Real Estate Corporation informs that in the first section of Nordica Residence RC, the ceiling of the 10th floor has been cast, now the construction of the vertical of the 11th floor is underway. This is reported by the construction project manager Volodymyr Shyrshov.
At the same time, the builders are laying the inner and outer walls. The second floor is 90% ready, the third floor is 75% ready.
In the second section, the builders complete the pile testing and start the foundation work.
It is also reported that preparations are underway for the start of piling works on the third section.
You can always find out more details on the purchase of apartments in Nordica Residence RC and the progress of its construction in the company's sales departments. Contacts are available at the link.