In the first section, the slab of the 10th floor is cast

October 04, 2021

RIEL Real Estate Corporation informs that in the first section of Nordica Residence RC, the ceiling of the 10th floor has been cast, now the construction of the vertical of the 11th floor is underway. This is reported by the construction project manager Volodymyr Shyrshov.

At the same time, the builders are laying the inner and outer walls. The second floor is 90% ready, the third floor is 75% ready.

In the second section, the builders complete the pile testing and start the foundation work.

It is also reported that preparations are underway for the start of piling works on the third section.

You can always find out more details on the purchase of apartments in Nordica Residence RC and the progress of its construction in the company's sales departments. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ЧП «Нордик Девелопмент»

Join our social networks
Contact us in convenient way
(044) 390-34-81
Feedback
The exchange rate as of 4/28/2024 is 39.67 UAH.
Sales departments
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Nordica Residence. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.