The Hryliata ceiling has been completed in the first building
RIEL Real Estate Corporation reports that the Hryliata ceiling has been fully completed in the first stage, in the first building of the Nordica Residence. Also, tiles have been laid on the floor of the first floor, cold passages have been finished, and the final painting is underway. The ground floor façade is 99% complete. The installation of the individual heating points and pumping station equipment is currently underway.
Landscaping works are ongoing and are 95% complete. Landscaping of the adjacent territory will be completed in spring.
The second building has completed the erection of vertical structures on the 21st floor and masonry walls on the 17th floor. The smoke removal system is being installed.
In the third building, the arrangement of roof parapets is being completed, and roofing works are underway.

Monolithic works in the parking lot are completed.
Asphalt paving and fencing works are underway on the territory of the complex.