Pumping station installation completed in the first building
RIEL Real Estate Corporation reports that the installation of a pumping station and an individual heating point has been fully completed in the first stage of the first building of the Nordica Residence RC. The whole building is also finished, and the arrangement of the transformer substation is nearing completion. Landscaping is 100% complete, except for the gardening, which will be completed in the spring. At the same time, the specialists submitted documents for putting the building into operation.
Windows and doors are being installed in the first parking lot, and preparations for the screed are underway.
In the second building, the floor slab of the 23rd floor has been completed, the masonry walls have been laid on the 18th floor, and the installation of prefabricated smoke removal and ventilation units is underway.
In the third building, the monolithic frame has been installed and the masonry work is nearing completion. At the same time, preparations for the installation of windows, roofing and elevators have begun.

Preparations for excavation and construction of access roads are underway in the third phase.